Quantitative Aptitude · Formula sheet
Time and Work: formulas and short tricks
Formulas and facts to remember
- Together: ab/(a + b)
- Three together: abc/(ab + bc + ca)
- M₁D₁H₁/W₁ = M₂D₂H₂/W₂
- Net pipe rate = 1/a + 1/b − 1/c
- With leak: fL/(L − f)
Key points
- Together, A and B finish in ab / (a + b) days.
- Work = Rate × Time.
- Use the LCM of the days as the total work to avoid fractions.
Core idea
- If A finishes a job in a days, A's rate is 1/a of the job per day.
- Work = rate × time; rates of people working together add up.
- Time and efficiency are inversely proportional: twice as efficient means half the time.
- If A does a fraction f of the work in d days, the whole work takes d/f days.
LCM (total work) method
- Step 1: take total work = LCM of the individual days.
- Step 2: each person's units per day = total ÷ their days.
- Step 3: add (or subtract) daily units, then divide total work by the result.
- Example: A 10 days, B 15 days → work 30 units, A 3/day, B 2/day, together 30 ÷ 5 = 6 days.
Standard results
- A and B together: ab/(a + b) days.
- A, B, C together: abc/(ab + bc + ca) days.
- A + B take x days and A alone a days ⇒ B alone = ax/(a − x) days.
- Pairs: if A+B, B+C, C+A take given days, add the three rates and halve to get A+B+C.
Men, women and wages
- M₁D₁H₁/W₁ = M₂D₂H₂/W₂ (men × days × hours per work).
- '10 men or 15 women' ⇒ 1 man = 1.5 women; convert everyone to one unit.
- Two equations like 12m + 16b in 5 days and 13m + 24b in 4 days: equate total work to find m : b.
- Wages are shared in the ratio of work done (efficiency × days worked), not in the ratio of days alone.
People leaving and pipes
- Someone leaves x days before the end: count backwards from the finish or count their days worked.
- Work done by all = sum of (each rate × days that person actually worked).
- Pipes: inlets add, outlets subtract; net rate = Σ(1/inlet) − Σ(1/outlet).
- A leak that empties in L hours turns a fill time f into fL/(L − f).
Short tricks
- The LCM method avoids fractions and is quickest under time pressure.
Common traps
- Do not add days; add rates (1/a + 1/b).
- Outlet pipes and leaks carry a minus sign in the net rate.
- When someone leaves early, the others still work for the full time.
- Wages follow work done, so a faster worker for fewer days may still earn more.
RankLao · Time and Work formula sheet · ranklao.com/formulas/quant-time-work