A and B work alternately, A on the first day, B on the second, and so on. A alone can finish the job in 12 days and B alone in 18 days. How long does the job take?
- A. 15 days
- B. 14 days
- C. 14 2/3 days
- D. 14 1/3 days
Correct answer: D. 14 1/3 days
Each 2-day cycle completes 1/12 + 1/18 = 5/36; seven cycles (14 days) finish 35/36. On day 15, A needs (1/36)/(1/12) = 1/3 day, so the total is 14 1/3 days.