Placement AptitudeHardWipro NLTH · Cognizant pattern

12 men can finish a job in 18 days. They start together; after 6 days, 4 men leave, and 6 days after that, 8 women join the remaining men. A woman does half the work of a man per day. How many more days are needed to finish the job after the women join?

  1. A. 6 days
  2. B. 12 days
  3. C. 10 days
  4. D. 8 days

Correct answer: D. 8 days

Total work = 12 × 18 = 216 man-days. Done: 12 × 6 = 72, then 8 × 6 = 48, leaving 96. 8 men + 8 women = 8 + 4 = 12 man-equivalents, so 96/12 = 8 days. 6 days treats the women as full men (16 workers).