One worker alone would need 100 days to finish a job. Work starts with 1 worker on day 1, and at the start of every following day one more identical worker joins. On which day is the job finished?

  1. A. Day 13
  2. B. Day 14
  3. C. Day 15
  4. D. Day 10

Correct answer: B. Day 14

After n days the work done is 1 + 2 + … + n = n(n + 1)/2 worker-days. 13 days give 91 < 100, 14 days give 105 ≥ 100, so the job ends during day 14.