A can finish a job in 15 days, and B is 50% more efficient than A. They work on alternate days, A on the first day. On which day is the job completed?

  1. A. Day 11
  2. B. Day 12
  3. C. Day 13
  4. D. Day 10

Correct answer: B. Day 12

A does 1/15 and B 1/10 per day, so each two-day pair does 1/6. After 10 days 5/6 is done; A on day 11 brings it to 27/30, and the remaining 3/30 = 1/10 is exactly B's work on day 12.