A finishes 1/3 of a job in 5 days and B finishes 2/5 of it in 12 days. Working together, how long will they take to finish 3/4 of the job?
- A. 7.5 days
- B. 10 days
- C. 6 days
- D. 9 days
Correct answer: A. 7.5 days
A alone takes 15 days and B alone 30 days, so together they do 1/15 + 1/30 = 1/10 per day. 3/4 of the job takes 7.5 days.
Practise more Advanced Quantitative Ability (Placement) questionsAdvanced Quantitative Ability (Placement): notes and key points
More Advanced Quantitative Ability (Placement) questions
- When, for the first time after 1 o'clock, are the hour and minute hands of a clock exactly 3 minute-spaces apart?
- The year 2000 was a leap year that began on a Saturday. Which of these years has exactly the same calendar as 2000?
- A month has five Fridays, five Saturdays and five Sundays. Which of the following is true?
- The 10th term of an arithmetic progression is 0. What is the sum of its first 19 terms?
- If 2ˣ = 3ʸ = 12ᶻ (all non-zero), then z equals:
- How many points (x, y) with integer coordinates satisfy x² + y² < 10?