A and B together finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How long would C alone take?
- A. 40 days
- B. 30 days
- C. 60 days
- D. 24 days
Correct answer: C. 60 days
2(A + B + C) = 1/12 + 1/15 + 1/20 = 1/5 → A + B + C = 1/10. C = 1/10 − 1/12 = 1/60 → 60 days.
Practise more Advanced Quantitative Ability (Placement) questionsAdvanced Quantitative Ability (Placement): notes and key points
More Advanced Quantitative Ability (Placement) questions
- Pipe A fills a tank in 12 hours and pipe B in 18 hours. They are opened alternately for one hour each, starting with A. How long does it…
- A clock gains 5 minutes every hour. It is set right at 8:00 a.m. What is the correct time when this clock shows 8:00 p.m. the same day?
- The calendar of 2026 will be repeated next in which year?
- What is the sum of all three-digit numbers divisible by 7?
- The 4th term of a geometric progression is 24 and the 7th term is 192. What is the sum of its first 6 terms?
- Given log₁₀ 2 = 0.3010 and log₁₀ 3 = 0.4771, find log₁₀ 0.0072.