Placement AptitudeModerateTCS NQT Advanced · Infosys pattern

A and B together finish a job in 12 days, B and C in 15 days, and C and A in 20 days. How long would C alone take?

  1. A. 40 days
  2. B. 30 days
  3. C. 60 days
  4. D. 24 days

Correct answer: C. 60 days

2(A + B + C) = 1/12 + 1/15 + 1/20 = 1/5 → A + B + C = 1/10. C = 1/10 − 1/12 = 1/60 → 60 days.