10 men can finish a job in 15 days and 15 women can finish it in 12 days. 5 men and 6 women work on it for 10 days. How many more men must then join so that the remaining work is finished in 2 days?

  1. A. 10
  2. B. 20
  3. C. 5
  4. D. 15

Correct answer: D. 15

A man does 1/150 and a woman 1/180 of the job per day. In 10 days the team does 50/150 + 60/180 = 2/3. For the last 1/3 in 2 days: 2(5 + x)/150 + 12/180 = 1/3, so (5 + x)/75 = 4/15 and x = 15.