A, B and C can finish a job in 6, 8 and 12 days respectively. All three start together; A leaves after the first day, and B leaves one day before the job is finished. How many days does the job take in all?
- A. 4 3/5 days
- B. 5 days
- C. 4 1/2 days
- D. 5 1/3 days
Correct answer: A. 4 3/5 days
Day 1 does 1/6 + 1/8 + 1/12 = 9/24. If the job takes T days, B works days 2 to T − 1 and C days 2 to T: (T − 2)/8 + (T − 1)/12 = 15/24, so 5T − 8 = 15 and T = 23/5 = 4 3/5 days.
Practise more Advanced Quantitative Ability (Placement) questionsAdvanced Quantitative Ability (Placement): notes and key points
More Advanced Quantitative Ability (Placement) questions
- A clock that loses 4 minutes every hour (of true time) is set right at 6 a.m. What is the true time when this clock shows 6 p.m. the same…
- How many leap years are there from 1601 to 2400, both years included?
- The first and last terms of an arithmetic progression are 5 and 95, and the sum of all its terms is 1000. What is the common difference?
- Three numbers a, b, c are in geometric progression, with a + b + c = 21 and a² + b² + c² = 189. What is b?
- How many digits does 12²⁰ have? (Use log₁₀ 2 = 0.3010 and log₁₀ 3 = 0.4771.)
- For real x, what is the largest value of (x² − x + 1)/(x² + x + 1)?