A can finish a job in 10 days and B in 15 days. They work together for 3 days, then A leaves and C joins B, and the two finish the job in 3 more days. How long would C alone take?
- A. 15 days
- B. 12 days
- C. 10 days
- D. 20 days
Correct answer: C. 10 days
In 3 days A and B do 3(1/10 + 1/15) = 1/2. B and C finish the other half in 3 days, so B + C = 1/6 per day and C = 1/6 − 1/15 = 1/10: 10 days.
Practise more Advanced Quantitative Ability (Placement) questionsAdvanced Quantitative Ability (Placement): notes and key points
More Advanced Quantitative Ability (Placement) questions
- In 24 hours, how many times do the hour and minute hands of a clock lie along one straight line (either coinciding or pointing in opposite…
- 15 August 1947 was a Friday. On which day of the week does 15 August 2047 fall?
- A thief escapes in a car at 40 km/h. Half an hour later, the police set off after him from the same spot at 50 km/h. How far from the spot…
- In a 1 km race, A beats B by 100 m and B beats C by 100 m. By how many metres does A beat C?
- A trader marks his goods 50% above cost and still makes a 20% profit after giving a discount. What is the discount percentage?
- ₹1500 is split between two investments at 6% and 8% simple interest per annum, earning ₹106 in total in a year. How much is invested at 8%?