A can do a job in 12 days and B in 16 days. With the help of C, the three finish it in 4 days and are paid ₹4800 in all, shared in proportion to the work each did. What is C's share?

  1. A. ₹1600
  2. B. ₹2000
  3. C. ₹1200
  4. D. ₹1400

Correct answer: B. ₹2000

In 4 days A does 4/12 = 1/3 of the job and B does 4/16 = 1/4, so C did 1 − 1/3 − 1/4 = 5/12. C's share = 5/12 × 4800 = ₹2000. An equal split would give ₹1600, and ₹1200 is B's share.