Placement AptitudeHardTCS NQT · Infosys SP
30 men can finish a job in 15 days. They start, but at the end of every 5 days, 5 men leave. In how many days is the job finished?
- A. 18
- B. 25
- C. 20
- D. 22
Correct answer: C. 20
The job needs 450 man-days. Days 1–5: 150; days 6–10 (25 men): 125; days 11–15 (20 men): 100; total 375. The last 75 man-days are done by 15 men in 5 days, so the job takes 20 days.
Practise more Advanced Quantitative Ability (Placement) questionsAdvanced Quantitative Ability (Placement): notes and key points
More Advanced Quantitative Ability (Placement) questions
- Over the full 400-year cycle of the Gregorian calendar, the 13th of a month falls more often on one day of the week than on any other…
- Today is Wednesday. What day of the week will it be 3¹⁰⁰ days from today?
- The sum of an infinite geometric progression is 4 and the sum of the cubes of its terms is 192/7. What is its first term?
- How many numbers are common to the arithmetic progressions 3, 7, 11, …, 407 and 2, 9, 16, …, 709?
- How many integers x satisfy log(1/2)(x − 3) > −2?
- If log₃ x × logx (2x) × log(2x) y = logx (x²), what is y?