30 men can finish a job in 15 days. They start, but at the end of every 5 days, 5 men leave. In how many days is the job finished?

  1. A. 18
  2. B. 25
  3. C. 20
  4. D. 22

Correct answer: C. 20

The job needs 450 man-days. Days 1–5: 150; days 6–10 (25 men): 125; days 11–15 (20 men): 100; total 375. The last 75 man-days are done by 15 men in 5 days, so the job takes 20 days.