12 men can complete a job in 20 days. After 8 days, 4 men leave the job. In how many more days will the remaining men finish it?

  1. A. 12
  2. B. 15
  3. C. 18
  4. D. 20

Correct answer: C. 18

Total work = 240 man-days; 96 are done. 144 remain and 8 men do it in 18 days.