A can finish a project in 20 days and B in 30 days. They start together, but A leaves 5 days before the project is completed. In how many days is the project completed?

  1. A. 12 days
  2. B. 15 days
  3. C. 17 days
  4. D. 14 days

Correct answer: B. 15 days

If the project takes t days, A works t − 5 days and B works t days: (t − 5)/20 + t/30 = 1 ⇒ 3t − 15 + 2t = 60 ⇒ t = 15. 12 days is the time if both worked throughout; 17 days adds the 5 days to the wrong base.