Placement AptitudeVery hardGoldman Sachs aptitude · Deloitte
At a firm, every project that was delivered on time used agile methods. Project Zeta used agile methods. Which of the following must be true?
- A. Project Zeta was delivered on time
- B. Project Zeta was delivered late
- C. Most agile projects at the firm were delivered on time
- D. Any project at the firm that did not use agile methods was not delivered on time
Correct answer: D. Any project at the firm that did not use agile methods was not delivered on time
'On time → agile' has the contrapositive 'not agile → not on time', which must hold. Concluding that Zeta was on time reverses the condition (affirming the consequent), a classic trap.
Practise more Logical Reasoning for Placements questionsLogical Reasoning for Placements: notes and key points
More Logical Reasoning for Placements questions
- Which number is the odd one out? 2197, 3375, 4913, 6859, 8000
- Find the missing number. The third number in each row comes from the first two by the same rule. Row 1: 6, 4, 34 Row 2: 8, 3, 35 Row 3: 5…
- A wall clock is hung so that at 3:00 its minute hand points north-east. In which direction does its hour hand point at 9:00?
- A three-digit number has a hundreds digit twice its units digit and a tens digit equal to the sum of the other two digits. Which of these…
- Seven people J, K, L, M, N, O and Q sit in a row of seven seats numbered 1 to 7 from west to east. Some face north and some face south. •…
- Seven people J, K, L, M, N, O and Q sit in a row of seven seats numbered 1 to 7 from west to east. Some face north and some face south. •…