Under AS 7, when it is probable that total contract costs will exceed total contract revenue, the expected loss is:

  1. A. Recognised as an expense immediately
  2. B. Recognised in proportion to stage of completion
  3. C. Deferred until the contract is completed
  4. D. Added to work-in-progress

Correct answer: A. Recognised as an expense immediately

Expected loss on a construction contract must be recognised as an expense immediately, irrespective of stage of completion.