Advanced AccountingVery hard
Under AS 7, when it is probable that total contract costs will exceed total contract revenue, the expected loss is:
- A. Recognised as an expense immediately
- B. Recognised in proportion to stage of completion
- C. Deferred until the contract is completed
- D. Added to work-in-progress
Correct answer: A. Recognised as an expense immediately
Expected loss on a construction contract must be recognised as an expense immediately, irrespective of stage of completion.
Practise more Accounting Standards & Ind AS questionsAccounting Standards & Ind AS: notes and key points
More Accounting Standards & Ind AS questions
- Under AS 9, interest revenue should be recognised:
- On amalgamation in the nature of purchase, assets taken over are Rs 15,00,000, liabilities Rs 5,00,000 and purchase consideration Rs…
- Under AS 25, revenue that is received seasonally or occasionally within a financial year should be:
- In consolidated financial statements, a venturer's interest in a jointly controlled entity is reported using:
- Under AS 29, the amount recognised as a provision should be:
- Under AS 26, internally generated goodwill is: