Advanced AccountingVery hard

A contract price is Rs 10 crore, costs incurred to date are Rs 4 crore and estimated total cost is Rs 8 crore. Under AS 7, profit recognised to date is:

  1. A. Rs 4 crore
  2. B. Rs 2 crore
  3. C. Rs 1.5 crore
  4. D. Rs 1 crore

Correct answer: D. Rs 1 crore

Stage of completion = 4/8 = 50%. Revenue = Rs 5 crore, cost = Rs 4 crore, so profit recognised = Rs 1 crore.