Cost and Management AccountingHard

Standard gang: 10 hours skilled at Rs 6 and 10 hours semi-skilled at Rs 4. Actual hours: skilled 12 and semi-skilled 8. The labour mix variance is:

  1. A. Rs 4 Favourable
  2. B. Rs 12 Adverse
  3. C. Rs 4 Adverse
  4. D. Rs 20 Adverse

Correct answer: C. Rs 4 Adverse

Skilled = (10 - 12) x 6 = 12 A and semi-skilled = (10 - 8) x 4 = 8 F. Net = Rs 4 Adverse.