Cost and Management AccountingHard

The material mix variance and the material yield variance together equal:

  1. A. The price variance plus the mix variance
  2. B. The yield variance minus the price variance
  3. C. The material cost variance
  4. D. The material usage variance

Correct answer: D. The material usage variance

Material usage variance = mix variance + yield variance. Adding the price variance gives the total cost variance.

More Marginal & Standard Costing, Budgeting questions