Cost and Management AccountingHard
The material mix variance and the material yield variance together equal:
- A. The price variance plus the mix variance
- B. The yield variance minus the price variance
- C. The material cost variance
- D. The material usage variance
Correct answer: D. The material usage variance
Material usage variance = mix variance + yield variance. Adding the price variance gives the total cost variance.
Practise more Marginal & Standard Costing, Budgeting questionsMarginal & Standard Costing, Budgeting: notes and key points
More Marginal & Standard Costing, Budgeting questions
- A product has P/V ratio 40% and fixed cost Rs 1,20,000. If fixed cost rises by 20%, the new break-even sales are:
- A process has a standard where 100 kg of input at Rs 9 per kg yields 90 kg of output. The standard cost per kg of output is:
- Product A has sales of Rs 60,000 with P/V ratio 30%, and product B has sales of Rs 40,000 with P/V ratio 50%. The overall P/V ratio is:
- The material cost variance equals:
- Opening cash is Rs 20,000. Current month sales are Rs 1,00,000 and previous month sales were Rs 80,000, with 50% collected in the month of…
- In marginal costing, the marginal cost of a unit consists of: