Cost and Management AccountingHard

Budgeted fixed overhead is Rs 1,20,000 for 6,000 units. Actual output is 5,500 units and actual fixed overhead is Rs 1,25,000. The fixed overhead volume variance is:

  1. A. Rs 10,000 Adverse
  2. B. Rs 5,000 Adverse
  3. C. Rs 15,000 Adverse
  4. D. Rs 10,000 Favourable

Correct answer: A. Rs 10,000 Adverse

Standard rate = Rs 20 per unit. Volume variance = (5,500 - 6,000) x 20 = Rs 10,000 Adverse.