Cost and Management AccountingHard

In a cost-plus contract, the contractee pays the contractor:

  1. A. A fixed price
  2. B. The market price
  3. C. Only a fixed fee
  4. D. Actual cost plus an agreed percentage or fee

Correct answer: D. Actual cost plus an agreed percentage or fee

A cost-plus contract reimburses actual cost and adds an agreed profit margin, which reduces the contractor's risk.