Cost and Management AccountingHard

Budgeted overhead is Rs 4,80,000 for 24,000 labour hours. Actual hours are 22,500 and actual overhead is Rs 4,60,000. Overhead is:

  1. A. Under-absorbed by Rs 10,000
  2. B. Over-absorbed by Rs 10,000
  3. C. Under-absorbed by Rs 30,000
  4. D. Over-absorbed by Rs 20,000

Correct answer: A. Under-absorbed by Rs 10,000

Absorbed = 22,500 x 20 = 4,50,000. Actual 4,60,000 exceeds it, so under-absorbed by Rs 10,000.