Cost and Management AccountingHard
In contract costing, work certified means:
- A. Cost incurred on the contract
- B. Work approved by the contractee's architect or engineer, valued at contract price
- C. Cash received from the contractee
- D. Cost of plant on site
Correct answer: B. Work approved by the contractee's architect or engineer, valued at contract price
Work certified is the work completed and approved by the contractee's representative, valued at the contract price.
Practise more Cost Accounting Methods & Techniques questionsCost Accounting Methods & Techniques: notes and key points
More Cost Accounting Methods & Techniques questions
- A school bus incurs Rs 72,000 a month, carries an average of 30 students and covers 2,400 km a month. Cost per student-km is:
- A contract is more than 50% complete. Notional profit is Rs 3,00,000 and cash received is 80% of work certified. Profit to be taken…
- Work done on a contract but not yet certified is valued at:
- In FIFO process costing, the cost per equivalent unit excludes:
- A lorry has an average load of 5 tonnes and covers 400 km during the period. The commercial tonne-km is:
- Joint cost is Rs 1,50,000. X sells for Rs 1,50,000 after further processing costing Rs 30,000, and Y sells for Rs 60,000 without further…