Financial Management and Strategic ManagementHard

When the discount rate is positive, the discounted payback period of a project is:

  1. A. Shorter than the payback period
  2. B. Equal to the payback period
  3. C. Unrelated to the payback period
  4. D. Longer than the simple payback period

Correct answer: D. Longer than the simple payback period

Discounting reduces the value of later inflows, so recovery takes longer than the simple payback period.