Under the risk-adjusted discount rate method of evaluating projects:
- A. A lower rate is used for riskier projects
- B. The risk-free rate is always used
- C. A higher discount rate is used for projects with higher risk
- D. The cash flows are ignored
Correct answer: C. A higher discount rate is used for projects with higher risk
A risk premium is added to the discount rate for riskier projects, reducing the present value of their cash flows.