Business LawsVery hard

Increased cost of performance due to a war-time closure of the Suez Canal making the route longer does not frustrate the contract, as held in

  1. A. Tsakiroglou & Co v Noblee Thorl GmbH
  2. B. Krell v Henry
  3. C. Taylor v Caldwell
  4. D. Hochster v De La Tour

Correct answer: A. Tsakiroglou & Co v Noblee Thorl GmbH

Tsakiroglou: mere increase in cost or inconvenience does not frustrate a contract.