Business LawsHard
Where a party sues for breach of contract but the loss cannot be proved with certainty, the court under s.74 may award
- A. Only nominal damages
- B. Reasonable compensation up to the named amount where the damages are difficult to assess
- C. Nothing
- D. Double the amount
Correct answer: B. Reasonable compensation up to the named amount where the damages are difficult to assess
Where damage is difficult to prove, the named amount as a genuine pre-estimate may be awarded as reasonable compensation (Kailash Nath Associates v DDA).
Practise more Business Laws (CA Foundation) questionsBusiness Laws (CA Foundation): notes and key points
More Business Laws (CA Foundation) questions
- A bailee finds that the goods bailed were damaged in a fire which broke out in his godown despite ordinary prudence. Under s.151 and…
- A watch is deposited with a jeweller for repairs. After repairs, the owner refuses to pay the charges. The jeweller's right is
- A person makes a general pledge of goods by a mercantile agent who has the goods but not the owner's consent to pledge. Under s.178, the…
- An agent who exceeds authority and enters a transaction with a third person binds the principal if the part within the authority can be…
- A principal who subsequently ratifies an act of an agent done without authority is bound by the ratification under s.196. Ratification…
- The agent is not personally liable on contracts entered into for a disclosed principal in the absence of an agreement to the contrary. But…