Where the time is not of essence under s.55, a party who fails to perform by the stipulated date may still perform later, but the promisee

  1. A. Is entitled to compensation for loss caused by the delay
  2. B. Can cancel with no liability
  3. C. Cannot claim loss
  4. D. Must accept without damages

Correct answer: A. Is entitled to compensation for loss caused by the delay

S.55(3): the promisee can claim compensation for any loss occasioned by the delay, if he gave notice of intention at the time of acceptance.