Behavioural CompetencyVery hard
Arjun learns that a data-centre server that the project relies on will be migrated next month, with no communication to the project team yet. What is the BEST course of action?
- A. Alert your manager and the infrastructure contact, ask for the plan and assess the impact to the project risks
- B. Wait for official notice before doing anything, since that has worked on earlier projects
- C. Tell the client the project is at risk now, to keep things moving for everyone
- D. Start redesigning the system on your own, because the team is under pressure already
Correct answer: A. Alert your manager and the infrastructure contact, ask for the plan and assess the impact to the project risks
Early inquiry with the right owners yields facts for the risk register; waiting or alarming the client without facts is premature.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- Nikhil, an offshore analyst, is asked by the onsite client lead to share daily progress updates three times a day, which Nikhil finds…
- Tanvi notices a teammate Shreya working very late each night and looking exhausted, and Shreya has just made two careless errors in the…
- Tanvi is asked to interview a candidate and notices a panel member Sandeep asking questions only to the female candidate about night…
- Isha receives harsh feedback from manager Swati on a status deck deliverable in front of two colleagues. The points are partly valid, but…
- Isha is asked by a manager outside Isha's project to copy the proprietary source code to a personal drive so he can 'work from home…
- Vikram notices that the project has no documented rollback plan for next week's database upgrade. The manager Yash says the team has done…