Behavioural CompetencyVery hard
Rohan notices that the project's milestone tracker reports green, but Rohan's own analysis suggests the data migration is two weeks behind. The status is reviewed by the client monthly. What is the BEST course of action?
- A. Assume the manager knows better and leave it, to keep things moving for everyone
- B. Update the status yourself to amber, because the team is under pressure already
- C. Share your analysis with the project manager with evidence and suggest updating the status or the underlying measures
- D. Mention it to the client at the review to be transparent, since that has worked on earlier projects
Correct answer: C. Share your analysis with the project manager with evidence and suggest updating the status or the underlying measures
The project manager owns the status; presenting evidence lets them correct it. Changing it yourself or telling the client first bypasses ownership.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- A senior colleague, Tarun, asks Kabir to mark a test case as 'passed' without running it because 'it always passes' and the deadline is…
- The delivery manager asks Nikhil to 'tidy up' the defect list so that the closed tickets count looks better before the client review. What…
- Lakshmi joins a stand-up call with an offshore Bengaluru team whose members are silent. Later, Lakshmi finds out two of them had concerns…
- Ananya is asked to join a call at 11 pm for a patch cut-over for the third night this week, while still expected to deliver normal work…
- Siddharth receives harsh feedback from manager Ajay on a estimate deliverable in front of two colleagues. The points are partly valid, but…
- During a governance call, the client's CTO asks Isha a question about security architecture that Isha cannot answer. Swati, the architect…