Behavioural CompetencyHard

Aarav learns that a data-centre server that the project relies on will be migrated next month, with no communication to the project team yet. What is the BEST course of action?

  1. A. Alert your manager and the infrastructure contact, ask for the plan and assess the impact to the project risks
  2. B. Wait for official notice before doing anything, to keep things moving for everyone
  3. C. Tell the client the project is at risk now, because the team is under pressure already
  4. D. Start redesigning the system on your own, since that has worked on earlier projects

Correct answer: A. Alert your manager and the infrastructure contact, ask for the plan and assess the impact to the project risks

Early inquiry with the right owners yields facts for the risk register; waiting or alarming the client without facts is premature.