Behavioural CompetencyVery hard
Imran is asked to train a client's new hire on deployment pipeline, but Imran's own project is stretched and the training has not been planned in the contract. What is the BEST course of action?
- A. Discuss it with your manager to confirm whether this is in scope, and agree a limited, scheduled session while the commercial team clarifies
- B. Agree to give unlimited training to please the client, since that has worked on earlier projects
- C. Refuse flatly as it is not in the contract, to keep things moving for everyone
- D. Provide training in off-hours without telling anyone, because the team is under pressure already
Correct answer: A. Discuss it with your manager to confirm whether this is in scope, and agree a limited, scheduled session while the commercial team clarifies
Checking scope with the manager and offering a bounded session balances goodwill and commercial discipline.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- Karan breaks a API gateway in the test environment while experimenting, blocking Farhan's team for the next two hours. Nobody knows the…
- Your mentee Kabir makes the same documentation mistake for the third time in a week despite earlier explanations. You are short on time…
- Isha notices Bhavna, a colleague on a different project, regularly posts clients' screenshots with internal URLs visible in public…
- Sneha is asked to train a client's new hire on data model, but Sneha's own project is stretched and the training has not been planned in…
- The client's legal team requests that Neha delete all transaction logs older than 30 days, but Neha's internal policy requires 12 months…
- Isha suspects a colleague Deepa is exaggerating hours on the project timesheet by about an hour a day. Isha has noticed it in the shared…