Behavioural CompetencyHard
Ananya notices that the project has no documented rollback plan for next week's go-live. The manager Ritu says the team has done this before and it will be fine. What is the BEST course of action?
- A. Accept the manager's view since the team has experience
- B. Postpone the change on your own authority
- C. Write a plan and keep it in your folder in case it is needed
- D. Offer to draft a short rollback plan, share it for review and ask Ritu to approve it before the change
Correct answer: D. Offer to draft a short rollback plan, share it for review and ask Ritu to approve it before the change
Drafting and getting the plan approved turns concern into a practical, shared control; keeping it private or unilaterally postponing misses either visibility or authority.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- Divya finds a defect close to the release deadline of a mobile app that affects a reporting field. The project manager Deepa suggests…
- Kavya accidentally emails a spreadsheet containing identity document personal data of 120 customers to the wrong external domain. No one…
- Vikram discovers that the onboarding requirements document says one thing, while the client's product owner said something different in…
- Kabir is asked by the client's finance team to adjust the licence figures in the invoice to match the budget, though the work done is as…
- Rahul receives a request from a colleague in another business unit for source code, saying it would help the proposal but the request has…
- Siddharth has completed a test suite faster than planned, with two days to spare, and Ajay's related task is lagging. What is the BEST…