Ananya notices that the project has no documented rollback plan for next week's go-live. The manager Ritu says the team has done this before and it will be fine. What is the BEST course of action?

  1. A. Accept the manager's view since the team has experience
  2. B. Postpone the change on your own authority
  3. C. Write a plan and keep it in your folder in case it is needed
  4. D. Offer to draft a short rollback plan, share it for review and ask Ritu to approve it before the change

Correct answer: D. Offer to draft a short rollback plan, share it for review and ask Ritu to approve it before the change

Drafting and getting the plan approved turns concern into a practical, shared control; keeping it private or unilaterally postponing misses either visibility or authority.