Behavioural CompetencyHard

Nikhil realises midway through a documentation task that the estimate was too low and the work will overrun by two days. The task is not on the critical path, and the team lead Yash is in meetings all day. What is the BEST course of action?

  1. A. Wait until the overrun becomes certain before telling anyone, since that has worked on earlier projects
  2. B. Cut testing steps to bring the work back to the original date, to keep things moving for everyone
  3. C. Message Yash now with the reason, the revised estimate and options to recover, rather than waiting for a meeting gap
  4. D. Absorb the overrun by working late and mention it at the weekly review, because the team is under pressure already

Correct answer: C. Message Yash now with the reason, the revised estimate and options to recover, rather than waiting for a meeting gap

A short written heads-up lets the lead plan around the slip even if not on the critical path; cutting tests or hiding it trades a visible delay for hidden risk.