Behavioural CompetencyHard
Nikhil realises midway through a documentation task that the estimate was too low and the work will overrun by two days. The task is not on the critical path, and the team lead Yash is in meetings all day. What is the BEST course of action?
- A. Wait until the overrun becomes certain before telling anyone, since that has worked on earlier projects
- B. Cut testing steps to bring the work back to the original date, to keep things moving for everyone
- C. Message Yash now with the reason, the revised estimate and options to recover, rather than waiting for a meeting gap
- D. Absorb the overrun by working late and mention it at the weekly review, because the team is under pressure already
Correct answer: C. Message Yash now with the reason, the revised estimate and options to recover, rather than waiting for a meeting gap
A short written heads-up lets the lead plan around the slip even if not on the critical path; cutting tests or hiding it trades a visible delay for hidden risk.
Practise more Behavioural Competency (Capgemini) questionsBehavioural Competency (Capgemini): notes and key points
More Behavioural Competency (Capgemini) questions
- Aarav accidentally emails a spreadsheet containing identity document personal data of 120 customers to the wrong external domain. No one…
- A banking client asks Rahul to add a extra user role that is not in the signed scope, saying it is 'a small thing' and promising a good…
- The client changes the UI design for the third time in two weeks. Siddharth's team is exhausted, the budget is nearly spent, and the…
- Rahul, an offshore analyst, is asked by the onsite coordinator to share daily progress updates three times a day, which Rahul finds…
- Imran finds a defect close to the release deadline of a payment patch that affects edge-case dates. The project manager Gaurav suggests…
- Neha is shadowing a steering meeting and hears the client mention that a competitor of Capgemini's offered a lower price. The sales lead…