Ananya promised the client's product team a data extract by Friday. On Wednesday, a dependency from another Capgemini team slips by three days, making Friday impossible. What is the BEST course of action?

  1. A. Wait until Friday and then explain the dependency failed
  2. B. Work through the weekend and hope to recover the three days
  3. C. Tell the client everything is on track and hope the other team catches up
  4. D. Inform your manager and the client today with the cause, a realistic new date, and what can be delivered on Friday as a partial

Correct answer: D. Inform your manager and the client today with the cause, a realistic new date, and what can be delivered on Friday as a partial

Early, specific communication with a revised date and partial delivery preserves trust; waiting until the deadline or hoping to recover removes the client's chance to plan.