Behavioural CompetencyVery hard

Rahul, a fresher, finds that the date-handling tutorial Rahul used for months was outdated, so several scripts in the project follow a deprecated approach. What is the BEST course of action?

  1. A. Inform the lead, list the affected scripts, and propose a phased fix prioritised by risk
  2. B. Fix everything in one large unreviewed commit, since that has worked on earlier projects
  3. C. Leave them until they break since they currently work, to keep things moving for everyone
  4. D. Tell the team the tutorial was wrong but do nothing, because the team is under pressure already

Correct answer: A. Inform the lead, list the affected scripts, and propose a phased fix prioritised by risk

Disclosing and prioritising remediation manages risk and gives the lead control; an unreviewed bulk fix or inaction both add risk.