Civil EngineeringVery hard
Constant head permeameter test: sample diameter 8 cm, length 10 cm, head 30 cm; 100 cm³ of water is collected in 120 s. The coefficient of permeability is
- A. 4.340 ×10⁻³ cm/s
- B. 5.526 ×10⁻³ cm/s
- C. 22.105 ×10⁻³ cm/s
- D. 1.382 ×10⁻³ cm/s
Correct answer: B. 5.526 ×10⁻³ cm/s
A = π8²/4 = 50.27 cm²; k = QL/(Aht) = 100×10/(50.27×30×120) = 0.005526 cm/s.
Practise more Geotechnical Engineering & Foundations (Civil) questionsGeotechnical Engineering & Foundations (Civil): notes and key points
More Geotechnical Engineering & Foundations (Civil) questions
- Falling head permeameter: standpipe area 1 cm², specimen area 20 cm², length 15 cm. Head falls from 100 cm to 50 cm in 900 s. The…
- A soil has k = 2×10⁻⁴ m/s and porosity 0.3. A hydraulic gradient of 0.2 acts. The seepage velocity, in mm/s, is
- A flow net under a dam has 5 flow channels and 8 equipotential drops. k = 5×10⁻⁵ m/s and net head 8 m. Seepage per metre length of dam is
- Upward seepage through sand with G = 2.65 and e = 0.8. The critical hydraulic gradient for quick condition is
- Water table is at 2 m depth. Soil above has γ = 16 kN/m³; below it γsat = 19 kN/m³. Taking γw = 9.81 kN/m³, the effective vertical stress…
- Water table is at 4 m depth. Soil above has γ = 18 kN/m³; below it γsat = 19 kN/m³. Taking γw = 9.81 kN/m³, the effective vertical stress…