Civil EngineeringHard

A clay layer drained at the top only takes 3 years to reach a given degree of consolidation. If the layer thickness were 3 times and drainage the same, the time for the same degree would be

  1. A. 27 years
  2. B. 9 years
  3. C. 1 years
  4. D. 81 years

Correct answer: A. 27 years

t ∝ H², so t = 3×3² = 27 years.