Civil EngineeringHard
A rapid sand filter plant treats 15 MLD at a filtration rate of 5 m/h. The total filter area required (ignoring backwash downtime) is
- A. 3000.0 m²
- B. 3125.0 m²
- C. 125.0 m²
- D. 62.5 m²
Correct answer: C. 125.0 m²
Q = 15000 m³/day = 625.0 m³/h; A = Q/rate = 125.0 m².
Practise more Hydraulics, Irrigation & Environmental Engineering (Civil) questionsHydraulics, Irrigation & Environmental Engineering (Civil): notes and key points
More Hydraulics, Irrigation & Environmental Engineering (Civil) questions
- To disinfect 5000 m³ of water at a chlorine dose of 3 mg/L using bleaching powder with 30% available chlorine, the mass of bleaching…
- To disinfect 2000 m³ of water at a chlorine dose of 5 mg/L using bleaching powder with 30% available chlorine, the mass of bleaching…
- A chlorine dose of 3.5 mg/L leaves a residual of 0.5 mg/L after the contact time. The chlorine demand of the water is
- A chlorine dose of 3 mg/L leaves a residual of 0.5 mg/L after the contact time. The chlorine demand of the water is
- A sewage sample has ultimate BOD L0 = 250 mg/L and rate constant k = 0.12 per day (base 10). The 3-day BOD at 20°C is
- BOD rate constant at 20°C is 0.15 per day. Using kT = k20(1.047)^(T−20), its value at 15°C is