Civil EngineeringHard

A crop has a base period of 120 days and a duty of 1000 hectares per cumec at the field. The delta (depth of water applied) is

  1. A. 72.000 m
  2. B. 1.037 m
  3. C. 10.368 m
  4. D. 0.120 m

Correct answer: B. 1.037 m

Δ = 8.64B/D = 8.64×120/1000 = 1.037 m.