Civil EngineeringVery hard
A building has a rectangular outer wall of centre-line dimensions 6 m × 5 m with 1 cross wall (each 5 m centre-to-centre). Foundation trench is 0.6 m wide and 1 m deep. Total excavation by the centre-line method is
- A. 17.64 m³
- B. 15.26 m³
- C. 16.20 m³
- D. 13.20 m³
Correct answer: C. 16.20 m³
Centre-line length = 2(6+5) + 1×5 = 27 m; V = 27×0.6×1 = 16.20 m³.