Civil EngineeringHard
Superelevation e = 0.07 is to be introduced by raising the outer edge of a 7 m wide pavement at a rate of 1 in 150 (rotation about the centre line, ignore widening and camber). The length of transition needed is
- A. 73.5 m
- B. 10.5 m
- C. 36.8 m
- D. 110.3 m
Correct answer: A. 73.5 m
Raise of outer edge relative to the inner = e×W = 0.490 m; length = N×raise = 150×0.490 = 73.5 m.
Practise more Transportation, Surveying & Estimation (Civil) questionsTransportation, Surveying & Estimation (Civil): notes and key points
More Transportation, Surveying & Estimation (Civil) questions
- Superelevation e = 0.05 is to be introduced by raising the outer edge of a 10 m wide pavement at a rate of 1 in 200 (rotation about the…
- Superelevation e = 0.06 is to be introduced by raising the outer edge of a 7.5 m wide pavement at a rate of 1 in 200 (rotation about the…
- A summit vertical curve with algebraic gradient difference N = 0.06 must provide SSD S = 150 m (eye height 1.2 m, object height 0.15 m, S…
- A summit vertical curve with algebraic gradient difference N = 0.04 must provide SSD S = 150 m (eye height 1.2 m, object height 0.15 m, S…
- Simplified lane capacity: spacing of vehicles S = 0.278Vt + l, where V = 40 km/h, reaction time t = 1 s and effective length l = 5 m…
- Simplified lane capacity: spacing of vehicles S = 0.278Vt + l, where V = 60 km/h, reaction time t = 1 s and effective length l = 4.5 m…