AccountingHard
Prime cost of 800 units is Rs 40,000 and wages are Rs 6,000. Factory overhead is 100% of wages. Works cost is:
- A. Rs 46,000
- B. Rs 50,600
- C. Rs 80,000
- D. Rs 40,000
Correct answer: A. Rs 46,000
Works cost = prime cost + factory overhead = 40000 + 6000 = 46000.
Practise more Fundamentals of Financial & Cost Accounting (CMA Foundation) questionsFundamentals of Financial & Cost Accounting (CMA Foundation): notes and key points
More Fundamentals of Financial & Cost Accounting (CMA Foundation) questions
- A firm's average profit is Rs 2,70,000 and the normal rate of return is 15%. Capital employed is Rs 6,60,000. By the capitalisation of…
- The net profit shown by the books was Rs 1,06,000. Later it was found that: (i) the sales book was overcast by Rs 18,000; (ii) closing…
- Fixed overheads are Rs 80,000 and the normal capacity 8000 units. Under absorption costing, fixed overhead per unit is Rs 10. If…
- A partner withdrew Rs 4,000 at the end of each month throughout the year. Interest on drawings is charged at 6% p.a. The interest…
- Under the single-entry (statement of affairs) method, opening capital was Rs 3,30,000 and closing capital Rs 7,90,000. During the year the…
- A trial balance did not agree and the difference was put to a suspense account. The only errors were: (i) a credit entry of Rs 3,000 was…