Budgeted factory overhead is Rs 1,30,000 for 20000 machine hours. Actual overhead incurred was Rs 1,40,000 for 18000 machine hours. Overhead absorbed at the pre-determined rate and the result are:

  1. A. Rs 23,000 under-absorbed
  2. B. Rs 23,000 over-absorbed
  3. C. Rs 13,000 under-absorbed
  4. D. Rs 10,000 under-absorbed

Correct answer: A. Rs 23,000 under-absorbed

Rate = 130000/20000 = 6.5/hr; absorbed = 6.5 x 18000 = 117000; actual 140000; under-absorbed by 23000.