AccountingHard
Under Taylor's differential piece-rate system, the standard output is 500 units per day, the normal piece rate is Rs 4 per unit, and the worker is paid 80% of the rate below standard and 120% at or above standard. A worker produces 46 units. His earnings for the day are:
- A. Rs 184
- B. Rs 221
- C. Rs 166
- D. Rs 147
Correct answer: D. Rs 147
Efficiency = 46/500 = 9%; rate applies 80% to all units: 46 x 3.2 = 147.20000000000002.
Practise more Fundamentals of Financial & Cost Accounting (CMA Foundation) questionsFundamentals of Financial & Cost Accounting (CMA Foundation): notes and key points
More Fundamentals of Financial & Cost Accounting (CMA Foundation) questions
- Fixed overheads are Rs 80,000 and the normal capacity 2000 units. Under absorption costing, fixed overhead per unit is Rs 40. If…
- Standard time for a job is 80 hours; actual time taken is 64 hours; hourly rate Rs 20. Under the Halsey premium plan (50% of time saved)…
- Budgeted factory overhead is Rs 2,70,000 for 10000 machine hours. Actual overhead incurred was Rs 2,50,000 for 12000 machine hours…
- A club received Rs 89,000 as subscriptions during the year. Subscriptions outstanding: opening Rs 5,000, closing Rs 6,000; subscriptions…
- Under Taylor's differential piece-rate system, the standard output is 200 units per day, the normal piece rate is Rs 5 per unit, and the…
- A material is used at a maximum of 60, normal 35 and minimum 10 units per week. Lead time: maximum 10 weeks, minimum 2 weeks (normal 6…