Business Laws & EthicsHard

An anticipatory breach of contract occurs when:

  1. A. A party repudiates the contract before the time for performance, entitling the other to sue at once or wait for the due date
  2. B. The contract is breached at the time for performance
  3. C. The contract is unenforceable
  4. D. A party performs earlier

Correct answer: A. A party repudiates the contract before the time for performance, entitling the other to sue at once or wait for the due date

Under s.39 and Hochster v. De La Tour, the promisee may rescind or elect to wait; if he waits and the contract gets frustrated, he loses remedy.