Business Laws & EthicsHard
An anticipatory breach of contract occurs when:
- A. A party repudiates the contract before the time for performance, entitling the other to sue at once or wait for the due date
- B. The contract is breached at the time for performance
- C. The contract is unenforceable
- D. A party performs earlier
Correct answer: A. A party repudiates the contract before the time for performance, entitling the other to sue at once or wait for the due date
Under s.39 and Hochster v. De La Tour, the promisee may rescind or elect to wait; if he waits and the contract gets frustrated, he loses remedy.
Practise more Business Laws & Ethics (CMA Foundation) questionsBusiness Laws & Ethics (CMA Foundation): notes and key points
More Business Laws & Ethics (CMA Foundation) questions
- A agrees to sell a house to B for Rs 20 lakh on 1 March. On 10 Jan, A informs B that he will not sell. B elects to treat the contract as…
- Quantum meruit, as a remedy, is:
- A contract is entered into where X offers a rare painting for sale, and Y accepts by telephone. Under the Indian law, the acceptance by…
- Which one of the following is a 'quasi-contract'?
- A contracts to sell specific goods to B, and the goods are not in a deliverable state. The property passes under s.21 when:
- Under s.22, where goods are in a deliverable state but the seller must weigh, measure, test or do something to ascertain the price, the…