Business Laws & EthicsVery hard
A cheque is not presented for payment within a reasonable time. If the bank later fails and the drawer suffers actual damage, under s.84 the drawer is:
- A. Liable in all cases regardless of the delay
- B. Discharged entirely, whatever the loss
- C. Liable only if the payee gives a fresh notice
- D. Discharged to the extent of the actual damage suffered by the delay
Correct answer: D. Discharged to the extent of the actual damage suffered by the delay
Section 84: if a cheque is not presented within reasonable time and the drawer suffers actual damage, he is discharged to the extent of damage.
Practise more Business Laws & Ethics (CMA Foundation) questionsBusiness Laws & Ethics (CMA Foundation): notes and key points
More Business Laws & Ethics (CMA Foundation) questions
- The validity period of a cheque in India, as per RBI directions effective from 1 April 2012, is:
- Where a banker wrongfully dishonours a customer's cheque despite sufficient funds, he is liable under s.31 to:
- Under s.123, a cheque is said to be crossed generally when:
- A drawer issues a post-dated cheque, and the cheque is presented before its date. Under s.138, the presentation is:
- A drawer issues a cheque as security for a loan. When the loan is repaid, the cheque is dishonoured. The accused argues no offence…
- Under s.141, where an offence under s.138 is committed by a company, the persons liable are: