Business Laws & EthicsVery hard
A contracts to deliver goods by 1 June, time being of the essence. He delivers on 5 June and B accepts them without notice. Under s.55:
- A. B cannot claim compensation for the delay unless he gave notice of his intention to do so at the time of acceptance
- B. B can claim compensation for the delay
- C. The contract is void
- D. B can claim the full price back
Correct answer: A. B cannot claim compensation for the delay unless he gave notice of his intention to do so at the time of acceptance
Under s.55(3), on accepting performance after the agreed time the promisee cannot claim compensation for non-performance at the time unless he gives notice of his intention.
Practise more Business Laws & Ethics (CMA Foundation) questionsBusiness Laws & Ethics (CMA Foundation): notes and key points
More Business Laws & Ethics (CMA Foundation) questions
- Where, in a contract, time is of the essence, and the promisor fails to perform by the stipulated time, the contract is:
- Which statement correctly states the rule on impossibility under s.56?
- A agreed to buy a ticket to watch the coronation procession from a room; the procession was cancelled because the King fell ill (Krell v…
- The difference between liquidated damages and a penalty under Indian law is that:
- Which damages are awarded to the plaintiff in breach of contract for loss of reputation or mental distress under Indian law, in general?
- Under s.64, a person who rescinds a voidable contract must: