Preventive and Social MedicineVery hard

PERT and CPM, used in health programme management, are techniques of:

  1. A. Network analysis for scheduling activities
  2. B. Sampling
  3. C. Costing
  4. D. Epidemic forecasting

Correct answer: A. Network analysis for scheduling activities

Programme Evaluation and Review Technique and Critical Path Method show interlinked activities and the critical path that determines project duration.