PERT and CPM, used in health programme management, are techniques of:
- A. Network analysis for scheduling activities
- B. Sampling
- C. Costing
- D. Epidemic forecasting
Correct answer: A. Network analysis for scheduling activities
Programme Evaluation and Review Technique and Critical Path Method show interlinked activities and the critical path that determines project duration.