CS FundamentalsHardGATE CS · PSU (ISRO/BARC)

Consider the schedule W1(A), R1(B), W2(A), R1(A), R3(B), W3(A), R2(A). Which statement is correct?

  1. A. Conflict serializable, equivalent to T1 → T3 → T2
  2. B. It is not conflict serializable
  3. C. Conflict serializable, equivalent to T3 → T2 → T1
  4. D. Conflict serializable, equivalent to T2 → T1 → T3

Correct answer: B. It is not conflict serializable

The precedence graph has both T1 → T2 and T2 → T1 (a cycle), so no serial order exists.